Key Dates
Public Information Centre #1
The Public Information Centre serves as an opportunity for residents to engage with the project team, review the contract drawings, and seek clarification on any project-related inquiries they may have. Everyone interested is welcome to attend the Public Meeting.
Time: 5:00 pm to 7:00 pm
Location: Council Chambers – Thorold City Hall, 3540 Schmon Parkway, Thorold, ON
Sullivan Ave and Towpath St Intersection Closure
The Sullivan Avenue and Towpath Street intersection is scheduled to close on Monday at 6.00am, September 21, for approximately two weeks.
https://letstalk.thorold.ca/44962/widgets/212688/documents/173601
Temporary Intersection Construction: Pine St. and Sullivan Ave. Intersection
On Monday, September 28 at 7:00 a.m. to Tuesday, September 29 at 6:00 p.m., the intersection of Pine St. and Sullivan Ave. will be under construction. The contractor is ahead of schedule and plans to attach the new sanitary main pipeline to the existing manhole located on Pine St.
Construction crews will occupy most of the intersection, however, they will yield the right of way to all emergency & essential services travelling north & south on Pine St.
Larger vehicles like busses and fire trucks will have to use extra caution when traveling north bound on Pine St., as they will have to veer left around the excavation. Smaller, passenger vehicles should not have any issues navigating the construction other than experiencing a delay which will cause a longer commute.
Those requiring access to Sullivan Ave., east of Pine St. will have to enter from Towpath or Front Streets.
Location Map:
Temporary Road Closure: Sullivan Ave. - Towpath St. to Front St.
Sullivan Avenue from Towpath Street to Front Street temporarily closed on Friday, October 2 and will remain closed for approximately three weeks. The City contractor is continuing to replace aging underground infrastructure and reconstructing the roadway within downtown Thorold.
As construction progresses along Sullivan Avenue, the closure will affect on-street parking and access to one entrance of Parking Lot 1 and the Thorold Community Credit Union parking lot. Both parking lots will remain accessible through their alternate entrances, and detour signage will be in place.
Please refer to the map below for an overview of the temporary road closure. The City contractor will maintain traffic flow where possible and keep existing sidewalks open, as long as possible. Sorry for any inconvenience. 
Notice Of Water Service Disruption
Time: 9:00 p.m. to approximately 12:00 a.m.
Please be advised that a disruption of water service to your property is required as part of the ongoing Construction actives talking place on Sullivan Ave.
Because many of the effected properties are commercial business or essential services, we have scheduled this work to take place in the evening hours.
Please make the necessary arrangements to store an adequate supply of water in advance of the shutdown.
Once water service has been restored, you may experience discolored water. If this occurs, please run an exterior tap or a large indoor tap (such as a bathtub or laundry tub faucet) until the water runs clear. If the issue persists after several minutes of flushing, please contact the City of Thorold 905-227-6613
We apologize for any inconvenience this disruption may cause and appreciate your patience and cooperation.